Extension of the existing district heating network
Project target
Changeover of the heat supply from, for example, night storage heating to district heating. The extension of the district heating network forms the basis.
Time period | 2011 to 2013 |
---|---|
Target group | THS, private house owners in Bottrop Boy |
Project idea | Initially approximately 80 flats of Vivawest GmbH in Reulstraße were connected to the district heat supply. The changeover of the heat supply of these buildings was completed by the beginning of the heating period 2011 / 12. A further 80 Vivawest flats in Kantstraße/Leibnizstraße are connected to the district heat supply in the following year. The CO2 reduction amounts, in the case of the changeover of the buildings with a heat output of 1,000 kW of low-tariff night-time electricity, to about 525 t/a and in the case of the changeover of the remaining units with 2,000 kW of mixed heating (gas, oil, electricity) to about 300 t/a. Hence about 825 t/a of CO2 is saved |
Project partners | City of Bottrop, steag Fernwärme GmbH |
Project status | Since 25.05.2011 ongoing |
Contact person | Stefanie Hugot |
Links |